Project:

Construction of a Data Centre

Procurement:

Construction Management

Our Role:

Commercial Risk Management was instructed to assist with commercial management and also procurement of package scopes.

Who we worked with:

Directly with the Site Team and Management. Based on site.

Timeframe:

Initial duration of commission was nine months with further input required on an ad hoc basis.

Outcome:

Detailed record of defective blockwork created and comprehensive cost of rectification account prepared. Completion and let to suit end user occupation requirements.

Lessons Learned:

Benefit of contemporaneous records.